§ 35.2-85.5. Cluster commercial development approvals required.  


Latest version.
  • (a)

    CUP and Concept Plan Required. No development, including the filing of a subdivision plat, within this a cluster commercial development shall be commenced until a Concept Plan and Conditional Use Permit have been approved by the City Council pursuant to section 35.2-11 (Applications Requiring Public Hearings Before City Council). Final approval of the conditional use permit is contingent upon approval of the final site plan.

    (b)

    Final Site Plan Required. Before any permit shall be issued for the erection of a permanent building in a proposed cluster commercial development may be issued, final site plan approval shall be required in accordance with section 35.2-14.2. (Site Plans).